5.0 Bill of quantities & Project Costs
..Back
|
Work / Description
|
Unit
|
Quantity
|
Cost (ex VAT)
|
|
Plant Hire
(Inc. operator & fuel)
|
|
|
|
|
15.5m 360 Excavator
|
Days
|
10
|
|
|
10t Hydrema
|
Days
|
10
|
|
|
JCB 3X
|
Days
|
10
|
|
|
Mobile Screener
|
Days
|
5
|
|
|
Plant Delivery Costs
|
|
|
|
|
Materials
|
|
|
|
|
Introduce Gravel / Stone
|
Tonnes
|
548
|
|
|
Excavate 2 Stage Berms & Off-River Refuges
|
Tonnes
|
430
(minimum)
|
|
|
Install 900mm
Twin-Wall Culvert Pipes
|
6m @ £80m
|
2
|
|
|
Erect Stock Proof Fencing
3 x HT (River Bank)
|
£2.44 per m
|
436m
|
|
|
Erect Stock Proof fencing
3 X HT (Off River Refuges)*
|
£440 ea.
|
2
|
|
|
Stiles & Hand Posts x 5
|
£38 ea.
|
5
|
|
|
Erect Post & Rail Cattle Drink
|
£150 ea.
|
1
|
|
|
Gravel for Cattle Drink
|
Tonnes
|
63
|
|
|
Gravel for Top Dressing Cattle Drink Rifle
|
Tonnes
|
46
|
|
|
Faggots**
|
2m @ £2.5 ea
|
10
|
|
|
Stakes
|
1m @ £2.5ea
|
20
|
|
|
Management
|
|
|
|
|
Water Vole Mitigation
|
Strimming /Trapping, etc.
|
|
|
|
Project Manager
|
£ day
|
12
|
|
|
Contingency Fund***
|
|
|
|
|
Total Ex VAT
|
|
|
|
|
Total Inc VAT
|
|
|
|
Notes:
Materials purchased directly by REEF will be subject to a 10% handling charge.
Q = Quote Provided
* Off river refuge costs are more expensive per m than river bank fencing due to the number of changes in direction and strainer post required,
*** Faggots may be able to made on-site for free depending on available materials.
** If project runs-over predicted 10 days, costs for plant hire per day are £+VAT Therefore it is wise to build into the budget a contingency fund to allow for unforeseen circumstances, events, etc.………….
All quotes are in appendix 2
NB: The above is available in Acrobat PDF form:

5-Bill-of-Quantities.pdf [65k]